Upgrade of the water supply system in the municipalities of Postojna and Pivka

currently under construction
Client Gorenje, d.d.
Location Municipality Postojna and Pivka
Scope Of Work Project management
Schedule 2016-2017

Project Detail

As the subcontractor of the company Gorenje, d.d. we are carrying out works within the project Drinking Water Supply in the Basin of the Ljubljanica – Set 1: Upgrade of the water supply system in the municipalities of Postojna and Pivka, namely the project set no. 3, which includes civil catching and waterworks of Malna and civil catching and waterworks of Korotan.

The works comprise of craftsman construction works, machine and technology installations and electrical installations, and are carried out under the general conditions of construction contracts for construction and engineering works planned by the contracting authority (FIDIC, red book).

The waterworks of Malna will be subject to installation of technological equipment for ultra-filtration of drinking water with a capacity of 150l/s. We also plan to renew the existing facility of the waterworks and of the civil catching and to upgrade the machinery and technological equipment within.

The waterworks of Korotan currently have a renewed roof construction, a new roof and a new extension, which will be used to install the new technological equipment for the ultra-filtration of drinking water with a capacity of 20l/s. Renovation of Korotan civil catching and installation of all the equipment necessary for the smooth operation of the waterworks are also a part of the planned works.